Banks are selling AI data center construction loans below face value. Subs on those jobs should check their payment protection now
HSBC sold its share of the $18 billion Project Jupiter construction loan at about 85 cents on the dollar, and ING and Société Générale have offered up to $800 million more in data center debt. A loan priced below face value means lenders see delay or completion risk. Electrical, mechanical and sitework subs on AI campuses should confirm their bond, lien and retainage position before the next pay application.
Banks that financed AI data center construction are selling their shares of those loans for less than face value. HSBC sold its roughly $300 million slice of the $18 billion Project Jupiter construction loan at about 85 cents on the dollar, and ING and Société Générale have offered up to $800 million more. For an electrical, mechanical or sitework sub working on one of these campuses, that price is a warning about the same risk you carry in your receivables: the project finishing late or not on the terms everyone planned.
What did the banks sell?
The figures below come from reporting by Bloomberg, Reuters and the Financial Times, as summarized by FinanceFeeds, The Standard and Briefs.
| Lender | What it sold or offered | Reported price |
|---|---|---|
| HSBC | About $300 million of the $18 billion Project Jupiter construction loan (New Mexico, 2.45 GW, part of Stargate) | About 85 cents on the dollar |
| ING | About $500 million across 12 loans, including a $25 million Jupiter slice and debt linked to Vantage Data Centers and CyrusOne. Bids due November 19 | Not disclosed |
| Société Générale | About $300 million tied to Project Lighthouse (Wisconsin) and Project Frontier (Texas) | Quoted above 90 cents, per the FT |
The Jupiter loans were quoted at about 89 to 91 cents in September, per earlier FT reporting cited by FinanceFeeds. That was the month Oracle sent the developer, a Blue Owl Capital unit, a force majeure notice seeking protection if delays kept the campus from opening in 2028. The project has faced delays on energy infrastructure, air-quality approvals and pipeline permits. Oracle has said the project remains on schedule.
HSBC's slice was less than 2% of the package, and the sale price does not show HSBC's actual loss. ING declined to comment on its sale.
Does this mean subs on these jobs won't get paid?
No. In a syndicated construction loan, one bank selling its slice usually changes who holds the debt, not how draws get approved and funded. Nothing reported here says any project has stopped funding pay applications.
What the price tells you is how lenders now rate the job. A buyer paying 85 cents is pricing in a real chance of delay, a renegotiated lease or a late finish. Those are the same events that slow a sub's pay applications, stretch retainage out by months, or turn a change order into a dispute. Fortune lists power shortages, construction delays, rising borrowing costs and local opposition as the pressures on data center developers, and the market selloff behind the ING sale points the same way.
What should a trade sub check this week?
Do this while the job still pays on time. Each protection is harder to use once payments slow.
- Get the payment bond. If the GC posted one, get a copy and read who the surety is, what the notice requirements are, and the deadline to make a claim. If there is no bond, know that before your exposure grows.
- Calendar every notice and lien deadline by job. Preliminary notices and lien filing windows are short and unforgiving. A missed date gives up the right no matter how large the balance is.
- Total your retainage by job. On a long data center schedule, retainage can grow larger than any single pay application. Know the number on each AI campus you're on.
- Read your pay clause. A pay-if-paid clause can shift the owner's funding risk onto you. Know which kind you signed before a payment is late.
- Watch for slow pay signs. Draws approved later than usual, partial payments, or new paperwork demands before release are early signs. Raise them with your GC the first week they happen.
- Price new bids for the risk. On a new data center bid, the owner's financing is part of the job's risk. Ask who is lending, and weigh retainage terms and payment timing the same way you weigh lead times.
What's still unclear?
ING's bids close today and the results have not been reported. The banks have not said whether they are selling because of a specific project or to cut overall exposure. And none of this means AI data center work is drying up. Oracle reports about $664 billion in remaining performance obligations.
The takeaway: a loan price is not a stop-work notice, but lenders are telling you they see more delay risk on these jobs than they did a few months ago. If you have AI data center work in backlog, spend an hour per job this week confirming your bond, your notice and lien dates, your retainage total and your pay clause.
- Why are banks selling AI data center construction loans?
- The banks have not said why. Reporting from Bloomberg and the Financial Times describes lenders cutting their exposure to AI data center debt after a selloff in AI stocks, with power shortages, permitting delays and local opposition weighing on some projects. HSBC sold a roughly $300 million slice of the Project Jupiter loan at about 85 cents on the dollar, and ING and Société Générale have offered up to $800 million of data center loans.
- Does a bank selling its share of a construction loan stop payments to subcontractors?
- Not by itself. In a syndicated loan, one bank selling its slice usually changes who holds the debt, not the draw process. The useful signal is the price: a loan trading in the mid-80s means buyers see real risk that the project is delayed or finished late, and that is the risk subs carry in their receivables.
- Which data center projects are tied to the loans being sold?
- According to the Financial Times as reported by FinanceFeeds, ING's portfolio includes a slice of Project Jupiter, the Stargate campus in New Mexico, and Société Générale's includes loans tied to Project Lighthouse in Wisconsin and Project Frontier in Texas. Bloomberg reported ING's portfolio also includes debt linked to Vantage Data Centers and CyrusOne.
- What should a subcontractor on an AI data center job do about financing risk?
- Get a copy of the payment bond if there is one, calendar every preliminary notice and lien deadline, track retainage held by job, and read the pay-if-paid or pay-when-paid clause in the subcontract. Do this while the job is paying on time, because each of these protections is harder to use once payments slow.